Subcontractor & Manpower Analytics

Audit-proof manpower reconciliation, labor variance and dwell-time analytics for project P875.

Contract Budget Allocation

On Budget

QAR 285.4M

+1.2%within approved cashflow

Daily Billed Labor Cost

Optimal

QAR 48.2K

-3.4%vs planned cap

Manpower Burn Rate

Controlled

94.2%

-2.1%under peak allowance

Site Productivity Index

High Output

1.08x

+8.0%above baseline

14-Day Deterministic Labor Forecast

Historical RFID ingress trend projected against master construction schedule

Confidence: 96.4%

Planned vs Actual Labor Headcount

Variance comparison across authorized trade contractors

Average Zone Dwell Times

Hours logged by subcontractor trades across hospital wings

Contractor
Planned Headcount
Actual Attendance
Audit Variance
Logged Biometric Hours
Ghost Worker Audit
Safety Induction
Al Sraiya MEP EngineeringMEP / Electrical
240228-5.0%41,320 h 0 Flags (Verified)
99.1%
Qatar Structural SteelStructural Steel
180162-10.0%29,880 h 0 Flags (Verified)
97.4%
Electro-Mechanical EnterpriseMedical Gas / Plumbing
150141-6.0%24,110 h 0 Flags (Verified)
98.8%
Al Rayyan HVACHVAC & Ductwork
130118-9.2%19,640 h 0 Flags (Verified)
96.2%
Falcon Fire ProtectionFire & Life Safety
9592-3.2%15,230 h 0 Flags (Verified)
100%
Doha Interior SolutionsFinishings & Joinery
130123-5.4%17,480 h 0 Flags (Verified)
95.6%