Variation Orders & Change Management

Contract Governance

Formal engineering change notices (ECN), scope amendments, cost impact assessments, and multi-tier client/consultant approvals.

Total Variations

1

Scope Notices

Cumulative Cost Impact

+QAR 120k

Budget Variance

Schedule Variance

+4 Days

Critical Path Impact

Approved Changes

0

Client Sanctioned

Variation Order Register

Showing 1 of 1 scope variation items

1 Changes
CR-P875-004Pkg: WP-01Consultant Review

Additional Dedicated Medical Exhaust Ducting (IPT L3 East)

Contractor: Al Sraiya MEP Engineering • Initiated by: Eng. Mounir Hadad (Al Sraiya MEP Project Director)

Cost Impact+QAR 120,000
Schedule+4 Days

Justification & Scope: Ashghal & HMC Infection Control request 60m of additional stainless-steel exhaust ducting with HEPA filter box to isolate new immunocompromised patient suites. (MoPH Revised Healthcare Code 2026 compliance requirement.)

Governance Approval Chain
Subcontractor PM: Eng. Mounir Hadad (APPROVED)
Main Contractor Lead: IMAR-Al Sraiya JV Lead (APPROVED)
Consultant Resident Eng: KEO Senior Resident Engineer (APPROVED)
Client Director (Ashghal): Ashghal Healthcare Project Director (PENDING)
Affected Zones: IPT-L3-East, IPT-L4-AHU