Executive Safety & Workforce Command

P875 Hamad General Hospital expansion & retrofit. Real-time telemetry synchronized across optical turnstile readers, RFID digital twin zones, and Edge AI vision gateways.

Digital Twin — Live Worker Concentration Heatmap

Real-time macro-zone occupancy computed from RFID portal reads and BLE mesh

Telemetry Streaming
Open Digital Twin
100%
GRID: BLDG-IPT · ELEVATION +14.500mBIM LOD-400 · RFID SPATIAL ANCHORS ACTIVE
IPT-L3-East
38 / 50 workers
76%
Al Sraiya MEP Engineering
IPT-L3-West
24 / 45 workers
53%
Doha Interior Solutions
IPT-L3-Core
9 / 20 workers
45%
Qatar Structural Steel
IPT-L3-Hoarding
5 / 10 workers
50%
Falcon Fire Protection
IPT-L4-AHU
1 / 6 workers
17%
Restricted Zone
IPT-L5-West
17 / 30 workers
57%
Electro-Mechanical Enterprise

Perimeter Portals

Zebra RFID turnstiles and optical lanes

Details

Gate 01 — North Main Ingress

Zebra FXR90 #1 · 10.87.5.11 · 99.98% uptime
3 in queue
L1 (IN)18/min
L2 (OUT)9/min
Recent Taps
Listening for RFID...

Gate 02 — Service Yard

Zebra FXR90 #2 · 10.87.5.12 · 99.91% uptime
1 in queue
L1 (IN)7/min
L2 (OUT)6/min
Recent Taps

Gate 03 — IPT Hoarding Access

Zebra FXR90 #3 · 10.87.5.13 · 99.42% uptime
L1 (IN)6/min
L2 (OUT)3/min
Recent Taps
Listening for RFID...

Gate 04 — South Logistics

Zebra FXR90 #4 · 10.87.5.14 · 99.87% uptime
2 in queue
L1 (IN)4/min
L2 (OUT)4/min
Recent Taps

Chronological Operational Event Feed

Live unified stream connecting RFID turnstile scans, AI safety detections, permit advances, and forensic audit entries

00:00:20

Access Authorized · Gate 02 — Inpatient Tower North Portal

Mustafa Akram (Al Rayyan HVAC) · QID: 2933408631 · Lane: Lane 1

Inspect
00:00:20

Access Authorized · Gate 04 — Services Laydown & Heavy Plant Gate

Rajesh Ali (Al Rayyan HVAC) · QID: 2953410275 · Lane: Lane 1

Inspect
00:00:20

Access Authorized · Gate 02 — Inpatient Tower North Portal

Imran Akram (Al Rayyan HVAC) · QID: 2973411919 · Lane: Lane 1

Inspect
00:00:20

Access Denied · Gate 04 — Services Laydown & Heavy Plant Gate

Faisal Iqbal (Al Rayyan HVAC) · QID: 29163400317 · Lane: Lane 2

Inspect
00:00:20

Access Authorized · Gate 02 — Inpatient Tower North Portal

Deepak Karim (Doha Interior Solutions) · QID: 2913401507 · Lane: Lane 1

Inspect
00:00:20

Access Authorized · Gate 04 — Services Laydown & Heavy Plant Gate

Kamal Ansari (Doha Interior Solutions) · QID: 2933403151 · Lane: Lane 1

Inspect
00:00:20

Access Authorized · Gate 02 — Inpatient Tower North Portal

Ahmed Karim (Doha Interior Solutions) · QID: 2953404795 · Lane: Lane 1

Inspect
00:00:20

Access Authorized · Gate 04 — Services Laydown & Heavy Plant Gate

Farhan Ansari (Doha Interior Solutions) · QID: 2973406439 · Lane: Lane 2

Inspect
00:00:20

Access Authorized · Gate 02 — Inpatient Tower North Portal

Khaled Karim (Doha Interior Solutions) · QID: 2993408083 · Lane: Lane 1

Inspect
00:00:20

Access Authorized · Gate 04 — Services Laydown & Heavy Plant Gate

Deepak Ansari (Doha Interior Solutions) · QID: 2913409727 · Lane: Lane 1

Inspect
00:00:20

Access Authorized · Gate 02 — Inpatient Tower North Portal

Kamal Karim (Doha Interior Solutions) · QID: 2933411371 · Lane: Lane 1

Inspect
00:00:20

Access Authorized · Gate 04 — Services Laydown & Heavy Plant Gate

Ahmed Ansari (Doha Interior Solutions) · QID: 2953413015 · Lane: Lane 2

Inspect
00:00:20

Access Authorized · Gate 02 — Inpatient Tower North Portal

Anwar Sheikh (Qatar Structural Steel) · QID: 2973400959 · Lane: Lane 1

Inspect
00:00:20

Access Authorized · Gate 04 — Services Laydown & Heavy Plant Gate

Hassan Yadav (Qatar Structural Steel) · QID: 2993402603 · Lane: Lane 1

Inspect
00:00:20

Access Authorized · Gate 02 — Inpatient Tower North Portal

Prakash Sheikh (Qatar Structural Steel) · QID: 2913404247 · Lane: Lane 1

Inspect
08:14:20

HSE Incident: Missing Safety Helmet (PPE Violation) (High)

AI Camera CAM-03 detected worker operating in IPT Level 3 Core without hard hat. · Zone: Central Elevator & Riser Stair Core

Inspect
14:10:00

HSE Incident: Unauthorized Non-Permit Zone Entry (Critical)

Worker entered restricted hospital air filtration chamber without active permit. · Zone: Air Handling Unit Room (NON-PERMIT RESTRICTED)

Inspect
07:15:00

PTW WO-1027: Stage 5 (Approved)

IPT Level 3 East Medical Infrastructure & Electrical Installation · Al Sraiya MEP Engineering · Quota: 20

Inspect
06:30:00

PTW WO-2026-P875-0142: Stage 6 (Active)

IPT Level 3 Medical Gas Piping Installation · Electro-Mechanical Enterprise · Quota: 25

Inspect
06:15:00

PTW WO-2026-P875-0143: Stage 6 (Active)

IPT Level 5 West Riser Cable Pulling · Al Sraiya MEP Engineering · Quota: 18

Inspect

24-Hour Manpower Distribution Curve

Scheduled contractual headcount vs actual RFID turnstile ingress over 24 hours (AST)

98.2% Correlation

Subcontractor Headcount & Permit Utilization

On-site workers vs approved permit quotas for Tier-1 trade contractors

Manage Contractors
ContractorTrade PackagePresent / PlannedCapacity UtilizationSafety Score
Al Sraiya MEP EngineeringMEP / Electrical228 / 240
95%
98.4% HSE
Qatar Structural SteelStructural Steel & Framing162 / 180
90%
97.1% HSE
Electro-Mechanical EnterpriseMedical Gas / Plumbing141 / 150
94%
99.2% HSE
Al Rayyan HVACHVAC & Specialist Ductwork118 / 130
91%
94.8% HSE
Falcon Fire ProtectionFire & Life Safety92 / 95
97%
100% HSE
Doha Interior SolutionsFinishings & Clinical Joinery123 / 130
95%
95.6% HSE